Each company’s beneficial locations for distributed energy resources can be found either on their utility-specific web portals or in their Initial Distributed System Implementation Plans (DSIPs).

Central Hudson’s beneficial locations can be found on their Distributed Generation web portal.
Granularity: Circuit, Substation, Transmission

Con Edison’s beneficial locations can be found on their Distributed System Platform web portal.
Granularity: Substation and Circuit

National Grid’s beneficial locations can be found on their System Data Portal. The interactive map is intended to help DER developers identify locations where there may be a capacity benefit on the distribution system from DER.
Granularity: Circuit

NYSEG and RG&E’s beneficial locations can be found in their 2023 Initial Distributed System Implementation Plan (DSIP). A web accessible portal is currently under development which will also host NYSEG and RG&E’s beneficial locations.
Granularity: Circuit

O&R’s beneficial locations can be found on their hosting capacity map.
Granularity: Circuit